|
Masonry materials may need to be heated prior to use to assure cement hydration in mortar. When placed, the mortar temperature should be in the range of
40' F (4.5' C) to 120' F (49' C). At temperatures of less than 40? F (4.5' C), cement hydration necessary for strength development is minimal. At temperatures of 120' F (49' C) or higher, flash set
is imminent. If ambient temperatures are falling below freezing, a minimum mortar temperature of 70' F (21' C) is recommended. Water is often the first material to be heated for two reasons: it is the easiest material
to heat and it can store much more heat, pound for pound, than the other materials used in mortar. Although recommendations vary as to the highest temperature to which water should be heated, Some specifiers put a maximum of
180' F (82' C) because higher temperatures pose a personnel safety hazard and could result in flash set. To avoid flash set, heated water should be combined with cold sand in the mixer before adding the cement. Sand is
typically delivered to the project and used in a damp loose condition. Therefore, even though sand piles are covered, it may be necessary to heat sand to thaw frozen lumps when temperatures fall below freezing. Generally, sand
is heated to about 50' F (10' C), although higher temperatures are permissible as long as the sand is not scorched and as long as resultant mortar temperatures do not exceed 120' F (49' C). Masonry units should
not have any visible ice on bedding surfaces when used, nor should the temperature of masonry units be less than 20' F (- 6.5' C) to avoid rapid lowering of mortar temperatures. Better productivity is often attained
using units having a minimum temperature of 40' F (4.5'C) . Masonry units should be kept dry, except that very high-absorption fired-clay brick may need to be wet ted, but not saturated, prior to use. Various techniques
can be used to heat mortar materials. Water is often heated in barrels or tubs. Sand piles can be heated using electric heating pads, by placing sand over a heated pipe, or by using steam heating systems. Masonry units are
usually heated on pallets in an enclosure or stored in a heated area.
Protecting Work Areas and Construction
Wind breaks, heated wall coverings, enclosures, or heated enclosures are used to maintain adequate mortar temperatures and to improve the comfort and efficiency of
masons and laborers. The level of protection required will depend on the severity of weather encountered. The Specification for Masonry Structures (ACI 530. 1 -95/ASCE 6-95/-95TMS 602-95) defines certain cold weather
construction requirements as summarized in Table 1. It includes provisions needed during the work day while masonry is being laid, as well as protection requirements for newly constructed masonry. Several means of implementing
these provisions are available to the mason contractor, recognizing that regional climatic differences and project-specific factors must be taken into account when selecting the most effective methods of protection for a given
project. Basic principles required for satisfactory cold weather masonry construction are well established as indicated in this publication and the referenced documents. The use of innovative construction and protection
techniques based on these established principles can often improve the effectiveness and efficiency of a cold weather construction program.
|